4. Conveyor Installation
Remove the front panel by lifting it straight up. (See Figure 1) Lift conveyor assembly ? by using “U” shaped
handles on each conveyor side bracket. Lower the conveyor into the two conveyor hanger brackets ? above the
grill plate on each side, so the four spacers on the sides of the conveyor rest on the bottom flange and the bottom
spacers are against the adjustment screws. The conveyor hanger brackets ? are factory adjusted. However, before
reinstalling the front panels apply power to the unit and run the conveyor to insure proper gear engagement. If gears
are not properly engaged adjust the conveyor by loosening the jam nuts on the conveyor hanger brackets and
adjusting the screw (see Figure 2) to set the conveyor to the correct height. Retighten lock nuts after adjustment is
complete.
a. To adjust the conveyor up into the drive gear, turn the conveyor adjustment screw clockwise. Use
a 7/16-end wrench to tighten the jam nut.
b. To adjust the conveyor away from the drive gear, turn the conveyor adjustment screw
counterclockwise. Use a 7/16-end wrench to tighten the lock nut.
5. Replace front panel.
6. Feeder Assembly
Install Feeder by fitting slots on back of feeder onto back panel studs located at top rear of unit.
7. Install Teflon Sheet (Optional)
Remove Feeder. Allow one end of the Teflon sheet to overlap the top of the rear panel to the rear
studs. Align the holes in the sheet with the stud heads and push the sheet over the stud heads. Balance
of the sheet will fit over the grill surface. Reinstall Feeder capturing Teflon Sheet between the feeder
and the top of the toaster.
Figure 2.